FRC 2018 (Power Up) => Program Management => Topic started by: Louis L on March 28, 2018, 09:48:36 PM

Title: Post-RIDE discussion summary
Post by: Louis L on March 28, 2018, 09:48:36 PM
A few students showed up for the debriefing. Here's what went on the white board.

Problems encountered at RIDE
What we can do in the next few weeks leading up to BC19. In parenthesis is a number and letter. The number (1,2,3) is priority. The letter (S,M,L) is size of task. Tasks with some element of uncertainty are bumped up one size from where they would otherwise be. Boldface text is current status. Tasks that provide new functionality have higher priority than those that are improvements over something we already have.
Lessons learned
Other things to do:
Open issues:
Title: Re: Post-RIDE discussion summary
Post by: Louis L on April 04, 2018, 11:40:51 PM
updated pincher speed fix.
Title: Re: Post-RIDE discussion summary
Post by: Louis L on April 09, 2018, 08:46:59 PM
updated intake, pot, max speed, and reach behind status
Title: Re: Post-RIDE discussion summary
Post by: Louis L on April 11, 2018, 09:58:57 PM
We gave the pincher a good workout tonight and the new faster motor doesn't grab as tightly as the old one; it can drop Cubes. So we put the old motor back. It's back to the slower speed but it holds great. Updated OP.
Title: Re: Post-RIDE discussion summary
Post by: Louis L on May 09, 2018, 11:37:02 AM
Made what is probably the last update to this thread.

We tested the climber last night and the camera the night before so all hardware mods are done. There is some minimal cleanup to do still - strap some wires down and grease the drivetrain. But aside from that the robot (hw and sw) are done. We have next week to practice before BC19.