#51
Things we learned and other useful info / Unit test before assembly
Last post by Louis L - February 23, 2018, 12:54:51 PM
When possible, test a component by itself before assembly.

Sometimes we get duds. Better to check out each component and know that it's good before assembly then to have to do debug later (not to mention having to swap out bad parts is often a pain).
#52
It's much, much easier to file rough & sharp edges before assembly. This should be obvious but it's often ignored. Also filing creates lots of dust and doing so after assembly risks getting the dust in sensitive electrical components or places where it can't be easily removed.
#53
Program Management / Re: Pre-WPI punch-list - Outsi...
Last post by Louis L - February 22, 2018, 10:31:25 PM

       
  • Wire up the 2 new batteries
  • Charge up all batteries
#54
Robot Software / Re: User Interface
Last post by Matt S - February 22, 2018, 03:22:01 PM
Buttons changed:

       
  • Nothing - Start button on controller
  • Nothing - Right stick on controller
  • Move arm to switch - X Button on controller
  • Move arm to exchange - A Button on controller
  • Fix Stuck Cube - Left Trigger:  This was modified to toggle which side of the intake had the slower wheel speed
Buttons added (these may need to be modified):

       
  • Raise intake - button 8 on the left joystick
  • Intake cube - button 9 on the left joystick
  • Move claw to level - button 10 on the left joystick
  • Close intake - button 11 on the left joystick
#55
Program Management / Re: Pre-WPI punch-list - Outsi...
Last post by Ed B - February 22, 2018, 01:04:53 PM
Reduce gripper weight 2/25

Improve gripper cube detection 2/25

Add gripper mechanical release mechanism. 2/25
#56
Program Management / Re: Pre-WPI punch-list - Robot...
Last post by Ed B - February 22, 2018, 01:01:47 PM
Rearrange sprocket and chain spreader to reduce bending torque on new shaft 2/25

Add bearing to middle of large sprocket 2/25

Replace torque transfer shaft 2/25

Shield intake limit switches 2/25
#57
Program Management / Re: Pre-WPI punch-list - Outsi...
Last post by Louis L - February 21, 2018, 10:24:37 PM

       
  • Finish BOM 2/26
  • Submit list of students attending WPI to school 2/25
  • Check school bus - verify just in case
#58
Program Management / Re: Pre-WPI punch-list - Robot...
Last post by Louis L - February 21, 2018, 10:04:53 PM

       
  • Install Gripper/Wrist assembly 2/25
  • Replace 1/2 inch shaft 2/25
  • More practice by Drive Team; see if Open Mesh radio fails
  • Test any new software
       - one crucial piece to test is grabbing the Cube from the starting position during Autonomous
  • Add pinch-guard on arm Relisted on 2/26 below
  • Protect Talon SRX on logic board from the flexible cable on the arm Relisted on 2/26 below
  • Check robot weight again Relisted on 2/26 below
#59
Program Management / Re: Pre-WPI punch-list - Outsi...
Last post by Louis L - February 21, 2018, 10:00:25 PM
Other stuff:

       
  • Button design 2/25
  • Make the buttons 2/25
  • Avatar design 2/26
#60
Program Management / Re: Pre-WPI punch-list - Outsi...
Last post by Louis L - February 21, 2018, 03:31:51 PM
Arcadia

       
  • need to build on Pablo's proof of concept WordPress interface to make a formal look & feel. This is a large task.
  • need to capture, edit, and create content. This is also a large task.
CAD

       
  • Need CAD models for Arcadia